Home
 

Detailed Chronology of Restoration Work on the Subotica Synagogue 1974-2000

Viktorija Aladjic


This chronology is based on an article by Radojka Tonkovic, of Subotica's Intermunicipal Bureau for the Protection of Cultural Monuments (IBPCM), which detailed restoration work on the Synagogue up until 1993. It can serve as a guide through a complex operation combining high hopes and missed opportunities, which began nearly two decades ago but is still far from complete.

1974

April 18 - The Assembly of the Community of the Society of Culture suggested to the Executive Committee of the Assembly Community of Subotica that the Synagogue be put under the protection of the law as a cultural monument.

1975

April 8 - The decree no. 02-241/2-75 of the Provincial Bureau for the Protection of Cultural Monuments in Novi Sad confirms that the synagogue bears the main features of a cultural monument.

June 4 - At the initiative of the president of the Assembly of the Commune, a Committee of experts examined the synagogue and concluded that because of longstanding neglect, the roof, the tiling and the decorative figures on the facade were damaged. The central part with the cupola was in the worst condition and was in danger of collapsing.

October 8-9. - On the demand of the Assembly of the Comune of Subotica an expert committee including bricklayers, architects, an engineer, a carpenter and a roofer inspected the cupola.

October 10 - The Cultural Center of Subotica prepaired the Survey, the order and the budget for the necessary steps for the conservaton-restoration of the synagogue. It stated, ”The cupola of the building has leaned to the north and inclined.”

1976

September 25 - Dr. Oskar Hrabovski, an engineer of architecture and an associate professor of the University of Architecture in Belgrade, presented a report on the state of the synagogue: ”Besides the artistic, aesthetic and material value, the building is unique and very rare in our regions ... the possible collapse of the cupola of the buiding will mean its total destruction of the synagogue...”

October 5 - The Executive Council of the Assembly of the Commune of Subotica issued a special subvention of 100.000 DIN to the Cultural Center, based on Dr. Hrabovski's report.

October 20 - A contract was signed between Laslo Gubi, a tinsmith from Horgos and the Cultural Center for tinning works on the roof of the synagogue in the amount of 35.000 DIN.

November 2-December 23 - The Craftsmen's Guild of the Cultural Center began cleaning the synagogue, putting glass in broken windows and doors, patching the holes on the building, installing lockers for electricity to supply the construction works, providing electricity, putting temporary glass in the vitrages, as a temporary protection of the synagogue.

November 3 - December 21 Tinsmith Laslo Gubi carried out the following works: the cleaning of the gutters, fixing the tiles and filling the holes on the roof and on the small cupolas.

November 11 - Endre Levai, the head of the technical department of the Culture Center asked the connection of the industrial current in the name of the Center for the synangogue.

December 23 - an inspection of the tinsmith works was been carried out.

1977

March - The Community of Self-managing Organizations of Subotica gave the means for the restoration of the synagogue.

April 15. - The Community of Self-managing Organization of Culture of Vojvodina provided 250.000.00 DIN to the Cultural Center in Subotica for the restoration and the revitalization of the synagogue.

July 12. - A committee including Endre Levai, a graduate engineer of architecture, Klara First, the president of the Jewish Community, Ladislav Horovic, the financial representative of the Jewish Community, Rudolf Vereb, a construction inspector, and Ante Bibic, a construction inspector submitted a report about the state of the synagogue to the Assembly of the Commune of Subotica in which it was emphasized that the central cupola was the most endangered part of the building.

October 20. - In the report of the completed works of the Technical Bureau of the Cultural Center it was stated that the synagogue was visited in the period between April 20 and October 10 in order to assess its condition.

December 3 - A contract was signed between Jooef Bognar, a carpenter from Subotica, and the Cultural Center for the necessary carpentry on the roof of the synagogue (90.000.00 DIN.)

December 6.-23. - Carpentry work was carried out in order to stop the the cupola from bending.

April 29. 1977. - July 26. 1978. - Expert associates of the Technical Bureau of the Cultural Center inspected the synagogue, measured it, stated the present situation, and drew technical documentation of the building.

1978

January 11. - A contract was signed between the Culture Center in Subotica and the Institute for photogrammetry of the Faculty of Geodesy of the University in Zagreb in order to carry out the photogrammetric survey. The cost of the works: 288.000 DIN.

March 23 - The team for the photogrammetric survey began the work.

November 2 - The Institute for photogrammetry of the Faculty of Geodesy of the University in Zagreb handed over to the Culture Center in Subotica the preliminary copies of the photogrammetric survey of the synagogue.

November 15 - At the Board meeting of the Culture Center a sum of 100.000 DIN was allocated to restore the cupola and install a lightning rod.

December 5 - A contract was signed between the Culture Center and the Workers' Organization for the designs at a cost of 133.000 DIN.

1979

January 9 - The Board for the protection of monuments of the Culture Center in Subotica prepared an approximate preliminary invoice for the restoration and revitalization of the synagogue in Subotica divided into phases from 1979 to 1984 with the intention of turning the synagogue into a multifunctional building for cultural purposes.

May - Standardprojekat designed the main plans for the installation of the lightning rod.

May - designed the main plans for the restoration of the main cupola.

July 12 - With the decree no. 03-501/2-79 the Provincial Institute for the Protection of Cultural Monuments agreed that the Cultural Center in Subotica could carry out the works according to the certified Project no. E-203 designed by for the installation of the lightning rod of the synagogue in Subotica.

September 4 - A contract was signed according to which the Jewish community of Subotica, on the basis of the decision of the Meeting of the members of the Jewish community held on September 24, 1978, unalterably gave the synagogue as a gift to the commune of Subotica. The signers of the contract were Mirko Vajcenfeld, the giver, and Bela Vas, the President of the Municipal Assembly, as the recipient.

September 10 - An expert committee consisting of Laslo Kiralj, an architect from the designing organization , Janos Salma, a technician from the Building Institute of the Socialist Autonomous Province of Vojvodina in Subotica, Endre Levai and Radojka Tonkovic from the Board of the Protection of Cultural Monuments inspected the synagogue and stated that new cracks had appeared on the cupola due to the torsional shifting. Thus it was decided that the reconstruction of the roof must be started at once on the basis of the Project E-203, designed by .

September 27 - The Council of the Cultural Center decided that a sum of 100.000.00 DIN from the total income of the Cultural Center should be given as an investment for the maintenance of the synagogue.

October - Samuel H. Abramson, the representative of the World Jewish Congress, visited Subotica to see the condition of the synagogue.

October - The Institute for City Planning and Geodesy in Subotica gave out the urbanistic-technical conditions for the revitalization of the synagogue and the repair of the façade under the no. U-194/79, for the request of the Cultural Center from Subotica as the investor. The designers: Piroska Mesaros, a graduate engineer of architecture, Gavra Braun, a graduate civil engineer, Silvia Derfler, a building technician, Branka Lazarev Boca, a graduate electrical engineer and Ervin Kladek, a graduate forestry engineer.

1980

February 28 - According to the Contract no. 04-15-16/64-2, the Community of Self-managing Organization of Culture of Vojvodina from Novi Sad gave 200.000 DIN to the Cultural Center in Subotica so that the work on the restoration and revitalization of the synagogue could be continued.

April 24 - The synagogue was entrusted to the Cultural Center in Subotica for protection, maintenance, restoration, adaptation and revitalizing.

October 10 - A contract was signed between the Cultural Center and the ”Zanat” Craftsmen's Guild from Subotica, according to which the Zanat undertook to carry out carpentry, tinning and construction works.

October 20 - December 23. - The first phase of the work on the reconstruction and restoration of the roof of the synagogue was finished. Scaffolding was erected under the cupola, then the whole construction of the cupola was lifted with a hydraulic press - with a crane weighing from 20 to 100 tons. The roof construction was lifted to its original height. The roof construction of the cupola was put back into its original position. The lifting of the cupola with the hydraulic presses was carried out between December 15-20.

October 29 - A contract was signed between the Cultural Center and the Building Company ”Novogradnja” and Labor Organization ”Standardprojekt” where the latter undertook to perform the technical and economic supervision of the works in process.

October 14 - The Cultural Center was assigned 2.000.000 DIN by the Municipality of Subotica for the maintenance and reparation of the synagogue.

November 26 - Laslo Kiralj was appointed to perform the technical and economic supervision of the adaptation of the cupola of the synagogue.

1981

February 10 - May 31 - The ”Zanat” Craftsmen's Guild carried out the following works on the synagogue: replacement of the decayed structure, replacement of some parts of the wooden construction of the cupola, making a mould for concrete gutters, tiling of the cupola and the side roofs.

May 14 - A contract was signed between the Cultural Center and ”Zanat” for the maintenance and restoration of the cupola and the rest of the synagogue. The total cost according to the contract was 1.960.000 DIN.

December 28. - The second phase of the works on the restoration, reconstruction and revitalizing of the synagogue was completed by the end of November in 1981. This phase included carpentry, tinning, tiling and the building work on the roof and the main cupola. Since new cogged tiles were expensive, a compromise was made whereby the old cogged tiles were coated with a special paint which extended their durability. With the completion of this phase, the synagogue was protected from rain. The unfinished parts of the roof were covered temporarily until the next phase of works.

1982

June 9 - The Executive Council of the Commune of Subotica charged the Intermunicipal Bureau for the Protection of Cultural Monuments (IBPCM) ”Severna Backa” from Subotica to carry out building work the synagogue.

April 12 - The Assembly of the Commune of Subotica granted 2.000.000 DIN to the IBPCM ”Severna Backa” for work on the synagogue in 1982.

The tinning and the carpentry on the roof and the erection of the scaffolding around the four side cupolas began.

1983

May 9 - The IBPCM took over the building in order to continue the work on the restoration, reconstruction and revitalization according to the agreed plan.

May 5 - December 28 - During this year building work carried out included the demolition of the half-hanging facade scaffolding for the four turrets, pulling down the decayed parts of the attic of these turrets and then building and plastering the attic. Carpentry work and tiling included the removal of the enameled cogged tile, the removal of the decayed construction, the replacement of planks in the niches and the replacement of all rotten parts of the wooden construction of the small cupolas, and tiling the roof with cogged tiles. The same work was carried out on the lower parts of the cupolas and the rubble was removed from the attic space. Tinning included the removal of the parts of the roof made of zinc plates and the manufacturing of the plates made of copper. The total cost of the works was 3.386.516,40 DIN.

1984

March 22 - June 30 - Work on the roof included the erection of the scaffolding for the tinning, the removal of decayed planks from the two small cupolas, installing new planks, and installing copper plates on the south-east cupola.

November 28 - A contract was signed between the IBPCM and the Craftsmen's Guild ”Zanat” for carrying out the tinning and carpentry on the synagogue's two small cupolas. The preliminary invoice of the contract was 1.355.936,50 DIN.

December 28 - The IBPCM prepared a plan for carrying out the reclamation, restoration and the reconstruction of the synagogue. The first phase would include the tiling in 1986, the reclamation of the façade in 1987 and the completion of the façade in 1988. The second phase would include the definition and the working out of the project documentation in the same period and the third phase would include the beginning of the works on the interior in 1989.

1985

Work on the small cupolas continued.

September 11 - With a decree, the Executive Council of the Assembly of the Commune gave the synagogue to the National theater for temporary use for the season 1985/86.

September - The Bureau for Urbanism and Geodesy produced the Urbanistic-technical terms for the temporary arrangement of the immediate surroundings of the synagogue.

1986

April 24 - A contract was signed between the IBPCM and ”Zanat” for the repair of the lightning rod of the synagogue. The price in the preliminary invoice of the contract was 2.694.588 DIN. Another contract was signed between them for the carpentry and tinning of the big cupola. The price in the preliminary invoice of the contract was 16.319.688,00 DIN.

March - ”Standardprojekt” completed the Plan for the repair of the damaged electrical installations in the synagogue.

May 22 - Endre Levai was appointed to supervise the work on the repair of the ligtning rod on the synagogue.

May 5 - December 1 - Work continued on manufacturing a platform in the big cupola for the scaffolding, making the scaffolding for the tinning and carpentry, preparing the mold for the sheet copper, replacing the decayed wooden components in the big cupola, preparing building material for the big cupola.

April - June - Manufacturing the lightning rod.

1987

January - The Society of Architects of Subotica, in cooperation with the Council for the Development and Building in Subotica, announced an internal competition to solicit ideas for the eventual use of the synagogue. Members of the Society of Architects could enter the competition. The closing date for the admission of the applications was May 16.

December 31 - The IBPCM brought declared that the synagogue and the surrounding complex of Jewish buildings - the ritual slaughterhouse and the building of the Jewish Community - was a monument.

1988

March 4 - A team of experts from the IBPCM inspected the synagogue and concluded that the National theater did not take adequate care of the building and performed various non-professional works and interventions on the interior and the exterior of the building for their own purposes which permanently damaged the condition of that unique cultural monument.

March 4 - The IBPCM awarded Filip Rihter the contract to carry out the painting of the central cupola of the synagogue. The price of the preliminary invoice of the work was 7.090.000 DIN.

May 15 - November 22 - The independent craftsman Peter Balint, a bricklayer from Subotica carried out the following works on the synagogue: The isolation of the external side of the walls, the repair of small damaged ornaments, replacing plaster ornaments, recessing the facade walls for installing the insulation, plastering the walls of the cupola, digging around the pillars, repairing the floors, plastering the inner sides of the walls.

May - The National theater temporarily vacated the synagogue so that the restoration of the painted ornaments of the central cupola could be carried out.

It was concluded that the National theater was devastating the immediate surroundings of the synagogue by erecting a tent-like construction.

June 29 - The Bureau for the inspection of building material of the University of Civil Engineering and the Research-Educational Institute for Civil Engineering in Subotica gave a report to the IBPCM about the testing of the qualitative characteristics of the built-in materials in the construction elements of the synagogue.

June 27 - October 17 - Preparatory work for the restoration of the painted decoration of the central cupola, plastering the central cupola. Filip Rihter surveyed the painted friezes and stencil patterned ornaments, surveyed and copied the friezes and ornaments, scraped the walls, painted and plastered the walls, whitewashed the walls and the ceiling with 4 year old lime, coated the walls with green soap, plastered the walls and the ceiling, soaped it for the second time, applied the first layer of paint, stenciled the colored friezes, and cut the stencils.

July 12 - An annex to the contract between the IBPCM and Filip Rihter regarding the painting of the central cupola was signed. The cost of the works was 10.180.000 DIN.

July - ”Standardprojekt” checked the statistical stability of the inner wire-lattice cupola. The main planner was Laslo Kiralj.

October - ”Standardprojekt” installed lavatories in the synagogue.

October 3 - Stained glass decorations were removed for restoration by Milan Stanisic from Sombor. These included 8 semi-circular vitrage windows with the size of 320 x 178 cm, 28 small vitrage windows in the cupola sized 62 x 98 cm and a new circular vitrage lantern on the cupola with a diameter of 300 cm.

October 18 - December 16 - Filip Rihter stenciled the friezes and the walls, cut the stencils, painted the stencils, and bronzed the plaster statues. Work stopped because of cold weather.

November 24 - The IBPCM and the designer Gabor Demeter completed the Main plan for the lavatories in the stairway areas of the synagogue.

1989

December 26, 1988. - April 19, 1989 - Works on the plumbing, the sewage system and the electrical installation of the lavatories were carried out.

February 17 - The National Theater resumed use of synagogue.

April - The Bureau concluded that during theater performances, the existing and the restored parts of the building were being damaged.

May 18 - A contract was signed between the IBPCM as the customer and the factory ”Opeka” from Osijek, the Basic Organization of Associated Labor ”Trudbenik” from Cakovo, for the manufacture of specially shaped.

August 14- A contract was awarded to Milan Stanisic, a stained glass maker from Sombor, for the restoration of 14 stained glass windows and pieces. The sum of money foreseen for the works was 129.030.000 DIN.

September - A committee of the UNESCO visited Subotica and the synagogue as well as the exhibition which was presented by the IBPCM about the restoration work.

September 11 - Samuel D. Gruber, the director of the Jewish Heritage Council of the World Monuments Fund in New York, visited the synagogue.

November 6 - The IBPCM of Subotica submitted a demand to the Community of Self-managing Organization of Culture of Vojvodina and the Committee for the Protection of Cultural Monuments in Novi Sad for the financial means to continue the tinning of the roof and the reclamation of the exterior covering of the synagogue. Total: 6.600.055.830 DIN (264.225 DEM). The claim was made by Gabor Demeter.

1990

January 3 -17 - An exhibition on ”The history of the synagogue in Subotica and its restoration” was held in Hódmezovásárhely in Hungary.

October 11 - The IBPCM submitted a claim for financing to continue the tinning of the roof and the reclamation of the exterior covering with the reconstruction of the ornamental items. Total: 3.016.898 DIN (430.985,43 DEM). The claim was written up by Gabor Demeter.

October 31 - The IBPCM sent a letter to the Cultural Foundation of the Commune of Subotica stating that 1.000.000 DIN was granted to the Bureau for the reconstruction and restoration of the external covering of the synagogue. In the first quarter of the year talks started with the Zsolnay factory in Pécs about the production of ceramics for the synagogue. However, the work could not be started until the contract was signed with the factory and the financing was only enough for part of items needed. On October 15, 1990, a claim was submitted for financing to continue the work.

December 3 - The Government of the Republic of Serbia declared the synagogue as a cultural monument of outstanding significance.

December 8 - The IBPCM asked the Foundation of Culture in Novi Sad for 1.290.000 DIN to work up a plan for the restoration and revitalization of the synagogue, so that it could apply for the UNESCO Art-nouveau architecture program. The idea was so that the synagogue could be put on the list of the world heritage within the framework of the ”project on the protection and restoration of the world's art nouveau through the Yugoslav architectural heritage”.

1991

January 15 - The Provincial Bureau for the Protection of Cultural Monuments in Novi Sad wrote to the IBPCM ordering that a restoration plan be drawn up and sent to the German and Norwegian committees of UNESCO within framework of the ”project of protection and restoration of the world's art-nouveau/jugendstil architectural heritage”.

January 23 - The specification of the elements made of burnt ceramics for the south-eastern and north-western facade no. 6-3/11 of the synagogue was carried out.

January 19 - Traces of curtains burnt by electric heaters were found inside the synagogue.

February - The Bureau submitted a claim to the Commune requesting that the National theater move out from the building because the synagogue was being devastated without a good reason.

April - The IBPCM published the terms for carrying out the restoration and reconstruction of the exterior of the building. Project coordinator was Gabor Demeter.

June - July - The Bureau recorded a video cassette about the condition of the building and presented it to the Commune.

September 20 - The IBPCM sent a letter to authorized institutions stating that the synagogue was being used in an unprecedented way and was being damaged by the National theater. An expert council of the IBPCM said the National theater should move out of the synagogue.

1992

Jozsef Kasza, the mayor of Subotica met Ester Votaw, one of the descendants of the family of Dezso Jakab's wife, Irena.

January 28 - The full amount of money was paid to the Zsolnay Porcelain factory in Hungary for the delivered ceramic facade units.

February 18 - The IBPCM addressed a letter to the Executive committee of the Commune of Subotica requesting that it order the National theater out of the synagogue and also requesting that the synagogue be turned over to the Bureau in order to protect it.

May 28 - The Executive Committee of the Commune of Subotica proposed a solution regulating activities of the National theater while the reconstruction of the theater's building in Subotica was taking place. According to this plan, it was necessary to start the decentralization of the Theater, that is, to provide conditions for various stage performances. Among other things, the 'Jadran' cinema would be used for 'classical' performances, and the Foundry would be used for the experimental theater. The buildings of the Theater and the synagogue would be used until work started on further reconstruction and restoration of both buildings.

August 12 - The IBPCM wrote to the Executive committee of the National theater stating that restoration work on the synagogue would begin October 1, so the National theater was asked to move out.

October 12 - A contract was awarded to the painter Istvan Anus to carry out preliminary work on the restoration of the painted decoration on the gallery of the synagogue. The agreed value of the works was 650.000 DIN.

October 27 - Anus was awarded a contract to restore the painted decoration on the gallery of the synagogue. The agreed value of the works was 1.155.000 DIN.

November 13 - The transfer of the synagogue was made between the National theater and the IBPCM. Damage was noted in the building during the transfer, and the National theater was asked to remove the garbage from the synagogue at its own expense.

1993

February 18 - Antun Rudinski, acting director of the IBPCM, informed the mayor that the restoration of the central chandelier of the synagogue was in its final phase. At the same time he stated that a further 7.500 DEM was needed for the restoration of the chandelier, plus another 795.815 DEM for restoration work on the interior of the building, and 1.300.667 DEM for restoration work on the exterior -- a total of approximately 2.200.000 DEM.

March 9 - Rudinski informed the representative of the South-Backa county that the available funds at the end of 1992 were enough only for the restoration of the central chandelier of the synagogue and for the preparation of the painting work on the gallery. There were no financial means for anything else.

March 10 - The IBPCM completed the ”Plan for the Restoration and Revitalizing of the Synagogue in Subotica”.

The mayor of Subotica Jozsef Kasza visited the United States. There he met Eszter Votaw and Samuel Gruber. After these meetings the search for international aid began for the restoration of the synagogue.

April 22 - The plan for restoration work for 1993 was present to the Executive committee of the Assembly of the Commune: the total replacement of the electrical installations, the renewal of the lighting apparatus, painting and decorating, totaling 48.720 DEM.

August 30 - Experts estimated that 600,000-700.000 DEM were necessary to repair the synagogue organ.

October 1 - Istvan Anus was awarded a contract to paint the altar of the synagogue. The cost of the preliminary invoice of the works was 1.115,40 DEM.

October 8 - The Sombor branch office of the Bureau for the financial supervision of the Republic of Serbia audited the financial records for work on the synagogue from 1989 to 1993. Its report stated that it could be concluded that the IBPCM received 277.830 DEM at the black market exchange rate in effect when the money was received, and paid out 110.947 DEM for work completed. Most of the financing arrived in 1990, a year in which no work was carried out. The first significant payments began in 1991, and because of the inflation over the period when work was halted, the money receive lost its value.

October 14 - Peter Balint was awarded a contract to carry out temporary measures to protect the large circular stained glass window above the main entrance of the synagogue. The cost of the preliminary invoice of the works was 3.894.000 DIN, or 354 DEM.

October 14 - Peter Balint was awarded a contract for inspecting the floors of the synagogue. The cost of the preliminary invoice was 802 DEM.

December 15 - The IBPCM prepared the preliminary measurements and the preliminary invoices for small urgent protective interventions for the synagogue in Subotica.

1994

April 19 - The IBPCM announced terms for the repair of the fence around the building of the synagogue.

May - The public Bureau for Urbanism, Construction and Planning of the Commune of Subotica announced the Urbanistic-technical terms for organizing the yard of the synagogue.

May 6 - The Serbian Ministry of Culture granted 70.000 DIN for the most urgent works on the synagogue.

May 9 - The Executive Committee of the Assembly of the Commune of Subotica, as the customer, and the IBPCM as the contractor, signed a contract for essential urgent interventions and supervision of technical protection of the synagogue. The customer was obliged to pay 59.121,40 new DIN and the Ministry of Culture of the Republic of Serbia would provide 68.915,40 new DIN.

May 9 - The Private Firm ¨Razvoj - Janic¨ was awarded a contraft to perform building guild works on the synagogue. The agreed cost of the works was 123.915,40 DIN.

May 16 - The Serbian Ministry of Culture granted the IBPCM 70.000,00 DIN for the most essential works on the synagogue.

May 16 - July 9 - ”Razvoj - Janic” carried out the following work: removing the ceramic tiles from the floor, digging and removing the earth, digging trenches for the sewage system, layering the gravel, stamping down the earth, concreting the floor tile, building manholes for the sewage system, disassembling the existing sewage system, installing the hydro-isolation in layers, transporting the surplus of the earth, installing thermo-isolation and metal framework and installing the gutters.

October - The IBPCM drew up plans for the rain drainage system for the synagogue.

1995

March 22 - The contract no. 101-1/11 was signed between the Executive committee of the Commune of Subotica as the customer and the IBPCM to work out a documentation album for the synagogue. The cost of the preliminary invoice of the contract was 1.000 DIN.

1996

The synagogue was put on the World Monument Fund Watch List of the World's 100 Most Endangered Cultural Monuments.

April 2 - An expert Committee of the IBPCM inspected the synagogue in order to assess the damage from a fire on March 31, 1996. The Committee found three crates containing the ornamental ceramic façade items produced at the Zsolnay factory in Pécs. Two crates were burnt up, while the third was open and the items taken out; some of them were broken.

June 25 - An expert committee of the IBPCM inspected the synagogue and found that the star of David's had fallen off the top of the main cupola. Since the peak of the lightning rod was fixed on it, the lightning rod had also fallen down.

1997

December 23 - Documentation for the property register of the synagogue was prepared..

1998

May 6 - The ”Integral” Building Firm submitted a demand for payment for storing the synagogue's pews.

September 22 - IBPCM experts Jagoda Alavantic, a graduate engineer of architecture, and Violeta Matesic, an architect-technician, prepared a preliminary invoice for the reclamation, reconstruction, restoration and revitalization of the synagogue. According to this preliminary invoice, the total funding needed was 4.091.322,42 DEM.

1999

February 25 - 27 - An international team of experts for prepairing the report about the state of the synagogue in Subotica with (Andras Román, Tamas Fejerdy, Klara Deák and Viktorija Aladjic) visited the synagogue to prepare a report on its condition. Their work was financed by the Samuel Kress Foundation, at the request of the World Monuments Fund.

2000

The synagogue was again put on the World Monuments Fund Watch List of the World's 100 Most Endangered Cultural Monuments.

December 7 - The new Jewish Heritage Grant program of the World Monuments Fund (WMF), sponsored by the Ronald S. Lauder foundation, granted $60.000 for the repair of the most damaged parts of the roof.